Immediately following the pouring of the Section 1 ground slab, construction began in preparation for the first PT (post-tensioned) slab one level above.

In an incredibly short amount of time the team erected the temporary support scaffolding in the northwest corner (above), and began the decking that would support the PT slab (below – far corner)

The scaffolding is spaced dimensionally for sheets of plywood. Special pieces of plywood are cut to fit around the future columns (areas where the reinforcing bars are sticking up above the deck level – below).

The grid is worked around unique elements, such as the elevator shaft shown here below, and the plywood decking will similarly be fitted up to the shafts. It’s important that when the slab is finally poured, the slab and shaft concrete should tie together.

This can be seen more clearly with the plywood deck in place (which was essentially done in a day with skill saws and nail guns).

Below you can see clearly how the plywood was crafted around the column areas and the large elevator shaft and pit.

Stepping back a bit (below), you can see two different, major operations going on at the same time. On the left, the vapor barrier is being installed over the crushed stone base in preparation for pouring the concrete of the next section of ground slab; and on the right, work has already begun on the reinforcing for the PT – post-tensioned – slab to be poured there.

Here are a couple of view of that work up on the deck.

As can be seen in these two views, there are a lot of different types of reinforcing being installed. The smaller, black bars are the normal reinforcing that strengthens concrete slabs, one set near the bottom of the slab, and another set near the top. In addition to these, however, are a set of what look like orange reinforcing bars. These are actually plastic-sheathed steel cables. Also noticeable is the fact that they don’t like flat but are draped higher near the columns and lower between columns. This has lot to do with how PT slabs work structurally.

In a PT slab, after the concrete is poured and has cured or set up a few days, the post-tensioning bars are pulled from each end, increasing the tension on them. This has two major effects on the slab. One is to cause the draped bars to want to straighten and raise up in the areas between columns. They can’t do this of course because of the weight of the concrete; but the stress they put on the concrete helps it resist the weight of parked cars and other loads on the slabs. The other effect is that the tensioning increases the compressive strength of the concrete in general, which increases its normal efficiency and allows the overall slab thickness to be reduced, saving materials. Working together, these two effects make for very strong floors.
Below is a look at the ends of the post tensioning rods (left side) where, if you look closely, you can see that the individual rods are threaded. These are the locations a hydraulic stressing ram will pull on them to increase the tension.

Notice also the little metal gadgets that look like spiders, but are often called chairs, that hold the reinforcing systems up off the deck. This is to prevent the reinforcing from touching the deck which would expose the reinforcing under the slab when the decking is removed from below and make the reinforcing vulnerable to corrosion.

One other critical detail is the wire that is being twisted around the places where the reinforcing bars cross over each other. This keeps the grid generally in the right place when the concrete is being poured so the structure will perform as it has been designed.
Then finally two more layers are added. First, the layer of electrical conduit (blue and gray) that goes on top of the bottom layer of reinforcing.

And then the top layer of reinforcing. The idea here is that the layers of reinforcing perform best when they are near (but not literally at) the upper and lower surfaces of the concrete; and other elements, like conduit, do best near the “neutral axis” (center) of the slab thickness where any effect they have on the structure will be reduced.
That’s a lot of energy going into Section 1, the northwest corner of the project; but it doesn’t mean that other areas are being neglected. Right next door, in Section 2, the ground slab is being poured so that it will be ready for the scaffolding and decking teams to start there work for the next PT slab.

That slab pour starts, of course, up at street level with concrete delivery and pumping.

Farther round the site, in sections 3, 4, and 5, the exterior wall reinforcing is being installed in preparation for the shot-crete walls. These walls need to be completed up to the level of the next floor before the PT deck is constructed so the wall and floor can be tied together.

And overhead – and often out of sight / out of mind – the tower crane lifts all sorts of things into and out of the site – a necessity when you’re working “in the hole” and can no longer drive in and out. Lifting things overhead is serious safety work; and a senior rigging director supervises every lift (steps 1 -4) and blows a loud whistle so everyone on the site is aware that loads are travelling above.

Finally, a look at Sections 1 and 2, ready for the next steps. In this photo (below) you can see that the scaffolding elements have already been stacked on the new ground slab in Section 2, ready to be set up.

And here in Section 1, the PT slab is nearly ready to be poured

This project is moving !












